STRIPPING TIME ( De-Shuttering):-


1) For columns, walls, vertical form works : 16-24 hrs

2) Soffit formwork to slabs : 3 days (props to be refixed after removal)

3) Soffit to beams props : 7 days props to refix after removal.

4) Spanning up to 4.50m : 7 days

5) Spanning over 4.50m : 14 days

6) Arches spanning up to 6m : 14 days

7)Arches spanning over 6m : 21 days